Turnkey cooling systems

In brief. A turnkey cooling system means one company is responsible for all of it: survey, feasibility study, design, manufacturing of NCT chillers, cooling towers and dry coolers at our own plant, supply of Thermax absorption chillers as the official representative in Russia and the CIS, installation by our own crews, handover after an integrated test run and 24/7 service; capacities from 100 kW to 50 MW and more, with more than 300 integrated projects since 2011.

A turnkey cooling system means one company is responsible for the whole system, from the site survey to service. We survey the site, work out options and a feasibility study, design, manufacture and supply the equipment, install it with our own crews, and commission and service systems with capacities from 100 kW to 50 MW and more. Such a system produces cooling, rejects the excess heat and delivers chilled water or glycol to every consumer: a machine tool, a reactor, an air handling unit, a server room.

We make NCT chillers, cooling towers, dry coolers and pump skids at our own plant in Sertolovo (Leningrad Region), and we supply Thermax lithium bromide absorption chillers as the official and exclusive representative of Thermax in Russia and the CIS since 2011. Since 2011 we have completed more than 300 integrated cooling projects, and the company's total is more than 780 completed projects for more than 1,000 customer companies.

What does the work include, and who is responsible for what?

Our team runs every stage, so the flow rate, temperature difference and winter mode come together in one calculation rather than at the interface between three contractors.

Stage What we do Timing and result for the customer
Survey and pre-design study heat loads, site conditions, layout options, techno-economic comparison 2–4 weeks; a chosen scheme and a budget you can defend
Design documentation (Stage P) design in our own engineering center with an SRO (self-regulatory organization) certificate, support during state expert review (Gosexpertiza) 2–3 months; a design that has passed expert review
Working documentation (Stage R) the "Cooling" and "Automation" sections 2–4 months; the drawings used for construction
Manufacturing and supply NCT chillers, cooling towers, dry coolers and pump skids from our plant, Thermax absorption chillers from the official representative; factory testing at the customer's request NCT cooling towers and chillers may be in stock; if not, 10–12 weeks
Installation foundations, steel structures, piping, electrical work, insulation, by our own crews one party responsible for the site
Commissioning and handover hydraulic tests, controls setup, an integrated test run, usually 72 hours under process load, bringing the system to design parameters a system handed over at design parameters
Service regular maintenance, diagnostics, online monitoring, 24/7 emergency service a warranty of up to 5 years with our installation and a service contract

The stages can also be ordered separately, but the interfaces between them are exactly where customers lose the most money.

What does a cooling system consist of?

Every system has four parts, and a mistake in one of them eats up the margin of the others:

  • cooling source: a compressor chiller, an absorption chiller or free cooling with outdoor air;
  • heat rejection: an open or closed-circuit cooling tower, a dry cooler, a remote air-cooled condenser;
  • hydraulics: pump skids, tanks, piping, filters. NCT pump skids are made for flows of 16–1,560 m³/h and heads of 10–100 m of water column, with 1+1 redundancy and automatic standby switchover;
  • controls and water treatment: control panels, SCADA, chemical water treatment panels for the open loop.

We are responsible for all four parts at once and make most of the equipment for them ourselves, so sizing one part does not break the calculation for another.

We will send the atlas of cooling system schemes (32 schemes with full piping on 46 pages: cooling towers, dry coolers, chillers, absorption chillers, heat pumps, with pros, cons and where to use each) by email or Telegram: request it on the resource page.

What water temperature is needed, and what goes into the loop: water or glycol?

The chilled water temperature is set by the consumer, and it determines both the choice of machine and how many hours a year the system can run without compressors.

Task Water temperature, supply → return What to consider
Air conditioning of a shopping mall, office, hotel 7 → 12 °C 1,000 kW of cooling needs about 172 m³/h of water in the loop; more in the article "Chiller and fan coil system" (in Russian)
A process that is fine with warm water 12 → 18 °C free cooling starts 6 K earlier than at 7/12 °C: partial below 11 °C outdoors, full below 5 °C
Ice water for food processing down to +2…+3 °C Thermax absorption chillers hold 8 → 3 °C and 6 → 2 °C; examples in the projects below
An outdoor loop that may stand idle in winter as the process requires water in a coil freezes within hours in frost; glycol or an intermediate heat exchanger is needed

Glycol transfers heat less well. On a 1,000 m³/h loop at 35 → 28 °C, 30% ethylene glycol protects against freezing down to −14 °C, but needs 7.5% more flow and a pump 34 kW more powerful. Food plants often allow only propylene glycol, pharmaceutical plants only water: this is the process engineer's decision. A step-by-step calculation is in the article "Closed-loop water cooling system" (in Russian).

Chiller and dry cooler with free cooling

Which cooling source to choose: a chiller, an absorption chiller or free cooling?

First we rule out options based on the hard constraints of the site: whether there is water, space, electrical capacity, waste heat. Then we compare the remaining options by operating cost over 15–20 years, not by the price of the machine.

Cooling source When we choose it Capacity in our range Example
Air-cooled chiller (NASA, NARA) no water on site, the machine stands outdoors or on a roof NASA 69–621 kW, NARA up to 1,740 kW chiller for the ATI plant (in Russian)
Water-cooled chiller with a cooling tower (NWSA, NWRA, NWCV) a large load, efficiency in hot weather matters NWRA 436–1,412 kW, NWCV 229–7,033 kW NWRA chillers for the Roshal Plasticizer Plant (in Russian)
Thermax absorption chiller steam, hot water from 80 °C, exhaust from a gas engine generator set or gas is available, electrical capacity is short 350 kW – 10.5 MW in a single machine Thermax absorption chillers from the official representative
Free cooling year-round load, for example a data center built into NASA chillers, dry coolers data center cooling
Dry cooler without a chiller the process accepts a liquid 3–5 °C or more warmer than the outdoor air, there is no make-up water, the coolant is glycol or a hot liquid at 60–70 °C NCT DC dry coolers from 300 kW, capacity is increased with modules NCT dry coolers

An absorption chiller uses 5–10 kW of electricity for pumps and controls per 1 MW of cooling. On the other hand, it rejects 1.7–2.45 kW of heat to the cooling tower for every kilowatt of cooling, versus 1.2 kW for a compressor chiller, so it needs a larger cooling tower. If less than 100 kW of cooling is needed, the temperature is below −5 °C or the site runs less than 2,000 hours a year, a compressor chiller is the remaining option.

The effect of the scheme on electricity costs is clear from a 1,000 kW chiller at 70% load around the clock (about 6,250 hours a year) and a tariff of RUB 7 per kWh. An air-cooled packaged unit with a COP of about 3 draws 333 kW from the grid, which is about RUB 14.5 million a year. A water-cooled chiller with a wet cooling tower (COP about 6) delivers the same cooling at 166 kW, about RUB 7.25 million a year. The price is cooling tower make-up water (about 2 m³/h for such a chiller), a more complex scheme and freeze protection in winter. For sites under 700 kW, standard schemes are usually simpler.

How much does a cooling system cost?

The price depends on the capacity, the cooling source, the redundancy requirements and the climate at the site. An engineer's consultation, layout options and a feasibility study are free of charge; design starts from RUB 300,000. Accurate selection instead of building in "extra margin" usually saves 15–25% of the equipment cost. Hardware price guides: NCT SVA series cooling towers from RUB 820,000, VR series from RUB 1,850,000.

What cooling systems have we already built?

Below are ten examples with a measurable result, and a table of all projects described on the website. This is only part of them: since 2011 we have completed more than 300 integrated projects, and many others are covered by non-disclosure agreements.

Mineral fertilizer plant, Cherepovets: a 3,766 kW chiller plant running on waste steam

Task. The mineral fertilizer plant needs to cool air for its fluidized bed units and granule cooling drums. In the warm season, production performance depends on it.

Solution. We designed a chiller plant with two Thermax 2B 5N C absorption chillers with a total capacity of 3,766 kW, running on steam, the plant's waste heat. We supplied a three-section cooling tower, air handling units for 360,000 m³/h of air, pump skids and controls, and carried out installation supervision and commissioning.

Result. According to the plant's technical director and chief engineer, the chiller plant performs better than specified in the design, and the work was completed on time. More about the project (in Russian)

Malt plant: +3 °C water from steam-fired absorption chillers

Task. During barley germination, the air in the shop must stay within 9–12 °C. For this, the steam absorption chillers had to deliver +3 °C water in the 8/3 °C mode, and that was the main challenge.

Solution. We developed the chiller plant design and supplied two Thermax steam absorption chillers of 1,500 and 2,500 kW, four NCT VR cooling towers, two NCT W2C chemical water treatment panels, panels with variable frequency control, controls on Siemens controllers and SCADA. We carried out installation supervision and commissioning.

Result. The machines deliver +3 °C at the outlet and hold the strict mode. In a 2019 reference letter, the plant's chief engineer confirmed that the equipment fully meets the stated specifications. More about the project (in Russian)

Cheese plant: ice water down to 2 °C

Task. A new cheese plant needed ice water for production and air conditioning for part of its premises. We won the tender for supply, installation supervision and commissioning in 2017.

Solution. We designed the chiller plant of the energy center: a 3,500 kW hot water driven Thermax 5G 7L C absorption chiller, two NCT VR4 cooling towers with basin heating and an NCT W2C chemical water treatment system.

Result. According to the customer's reference, the absorption chiller was delivered in 20 weeks and the cooling towers ahead of schedule, with no complaints about the equipment. The machine runs in two modes: 12 → 7 °C and 6 → 2 °C. More about the project (in Russian)

Russia's first trigeneration (CCHP) for greenhouses

Task. A greenhouse complex in the Sverdlovsk Region needed cooling to air-condition its packing area. The site has waste heat: hot water from gas engines and the boiler house.

Solution. We designed the system and supplied two Thermax LT 12 C absorption chillers of 400 kW each that cool water to +3.5 °C, two NCT VR1 cooling towers, controls with online monitoring and NCT W0C chemical water treatment. We carried out installation supervision and commissioning.

Result. Heat and electricity costs per hectare were cut in half, the energy efficiency of the complex reached 92%, and the payback period is 5 years. More about the project (in Russian)

Shopping center: more than RUB 7 million in savings per year

Task. A shopping center in Saratov needed air conditioning with a low cost of cooling. In summer, the heat of the flue gases from its gas engines goes to waste.

Solution. In 2014 we supplied two Thermax 5G 6L C absorption chillers of 2,200 kW each for the trigeneration system and carried out installation supervision and commissioning.

Result. Cooling is produced from waste heat; the annual savings from the absorption chillers exceed RUB 7 million. More about the project (in Russian)

Cooling from the heat of gas engine units

Task. The customer's two cogeneration (CHP) plants, Davydovka and Osobino, needed low-cost cooling for air conditioning. The waste heat of the gas engine units was chosen as the source, and the supplier was selected through tenders in 2013.

Solution. We designed the system, supplied a 651 kW Thermax LT 14C and a 280 kW Thermax LT 10C absorption chiller and an open NCT cooling tower, and carried out installation supervision and commissioning. Both machines were started up in 2015, exactly on the contract date.

Result. The customer got a trigeneration complex; according to the customer, it covered 90% of the production facilities' electricity needs and provided almost 30% of their heat consumption. Both plants sent letters of thanks. More about the project (in Russian)

Absorption chillers delivered a month ahead of schedule

Task. In summer, the plant has nowhere to use the heat from its gas engine energy center. The challenge was to coordinate the operation of the plant and the absorption chillers during the transition period and at low load, under the customer's strict reliability requirements.

Solution. We designed the system and supplied two Thermax 5G 4L C absorption chillers of 1,100 kW each and two cooling towers, and carried out installation supervision and commissioning.

Result. The plant got low-cost cooling from waste heat and machines with a service life of 25 years without major overhauls. According to the customer's letter, the absorption chillers from India and the cooling towers from Belgium arrived a month ahead of schedule despite sanctions-related delays. More about the project (in Russian)

Engineering center: cooling, heating and hot water from the same machines

Task. The building needs cooling for air conditioning, heat for space heating, and hot water. The usual scheme is separate chillers and separate hot water boilers.

Solution. We proposed and designed a chiller plant with two natural gas fired Thermax GD 20C chiller-heater absorption machines (1,200 kW of cooling) and four closed-circuit cooling towers, helped with the design documentation, and carried out installation supervision, commissioning and service.

Result. In summer the machines provide cooling and hot water, in winter heating, and they use 40% less gas for hot water than hot water boilers. In 2018 the customer sent two references: on the supply and on the service. More about the project (in Russian)

Pipe plant: replacing machines that had run for 25 years

Task. The automated process control systems need continuous cooling. It was provided by two Trane absorption chillers that had been in operation for 25 years.

Solution. In 2012 we supplied the first 1,650 kW Thermax HS 50C-CU absorption chiller and commissioned it in a record short time. In 2013 we signed a contract for a second identical machine.

Result. Both Trane machines have been replaced. After the first machine, the plant chose us as the supplier for the second one as well and sent a letter of thanks. More about the project (in Russian)

Replacing a failed cooling tower in winter

Task. At an automotive components plant, an Evapco cooling tower in operation since 2010 failed. The new one had to be installed in winter and operated through the cold season; the supplier was selected through a tender.

Solution. We supplied three NCT SVA-1 cooling towers from stock at very short notice and carried out installation supervision and commissioning.

Result. The cooling towers cool the process line and cope with operation in winter. More about the project (in Russian)

All projects: site, industry, capacity

Select an industry to show only its projects in the table. Capacity is given where it appears in the project description; for cooling towers it is the heat load or the water flow rate.

SiteIndustryEquipmentCapacity
Mineral Fertilizer Plant, CherepovetsChemicals and petrochemicals2 Thermax 2B 5N C steam-fired absorption chillers, cooling tower, supply air handling units3,766 kW of cooling
Oil RefineryChemicals and petrochemicalsNCT VR cooling tower, control panel—
Petrochemical Plant, Blagoveshchensk (Bashkortostan)Chemicals and petrochemicalsThermax SS 40A-CU steam-fired absorption chiller1,640 kW of cooling
Petrochemical Plant, Shymkent (Kazakhstan)Chemicals and petrochemicalsNCT SVA-2 cooling tower, control panelflow rate 70 m³/h
SvetlogorskKhimvolokno CompanyChemicals and petrochemicalsfour-cell NCT VR1S cooling tower—
Tire Recycling PlantChemicals and petrochemicalsNCT VR cooling tower, W2C water treatment—
Uralkhimplast plant, Nizhny TagilChemicals and petrochemicalsThermax 2B 3M C steam-fired absorption chiller1,250 kW of cooling
Belorusneft Power Generation FacilitiesPower generationThermax LT 14C and LT 10C absorption chillers, NCT cooling tower651 + 280 kW of cooling
Gas Turbine Power PlantPower generationThermax 2D 5M C absorption chiller running on gas turbine exhaust3,150 kW of cooling
Armenian Branch Pargev Dairy PlantFood industryNCT SVA-2S cooling tower—
Bellakt Baby Food PlantFood industryNCT SVA-0 cooling tower—
Chips and Croutons PlantFood industryThermax 5G 4L C absorption chiller, NCT VR3 cooling tower1,000 kW of cooling
DEP LLP Dairy PlantFood industryNCT VR1 cooling towers, pump skids, controls—
Döhler food ingredients plantFood industryThermax TZC L5 G4 absorption chiller, NCT VR4 cooling towers, 2 dry coolers for free cooling, W2C water treatment1,500 kW of cooling
FRUIT ART LLP Fruit and Berry Freeze-Drying PlantFood industryNCT SVA-1 cooling tower, pump skid, control panel—
Grodnoagroinvest Rapeseed Oil PlantFood industryNCT SVA-1 cooling tower, control panel—
Kobrin Butter and Cheese PlantFood industryNCT SVA-1 cooling tower, control panel600 kW
Kursky Solod Malt PlantFood industry2 Thermax steam-fired absorption chillers, 4 NCT VR cooling towers1,500 + 2,500 kW of cooling
Lebedinskaya UsadbaFood industry2 NCT SVA cooling towers—
Libella Bottlers Almaty LLPFood industryNCT SVA-1 cooling tower, PU-30/20 pump skid—
Molochny Mir PlantFood industryNCT VR1 cooling tower, VFD control panel2.3 MW, 100 m³/h
Sei-Nar LLP Agricultural CompanyFood industryNCT SVA cooling tower, control panel, pump skids—
Syry Kubani Cheese and Dairy PlantFood industryThermax 5G 7L C absorption chiller, 2 NCT VR4 cooling towers3,500 kW of cooling
Teplichnoye JSC Greenhouse ComplexAgriculture and greenhouses2 Thermax LT 12 C absorption chillers, 2 NCT VR1 cooling towers2 × 400 kW of cooling
Vyborzhets Agricultural ComplexAgriculture and greenhouses2 Thermax absorption chillers, NCT VR4 cooling towers3.8 MW of cooling
Aktivny Komponent Pharmaceutical CompanyPharmaceuticals2 Thermax absorption chillers, NCT VR3S cooling towers2 × 1,430 kW of cooling
Nesvizh Plant of Medical PreparationsPharmaceuticalsNCT VR0S cooling tower, VFD control panel—
AMK MetizMetallurgy, machine building and electronicsNCT SVA-1 mini cooling tower—
BobruiskAgroMash Agricultural Machinery PlantMetallurgy, machine building and electronicsNCT SVA-1 mini cooling towers, Thermax absorption chiller—
Duvon Rus Automotive Components PlantMetallurgy, machine building and electronics3 NCT SVA-1 cooling towers from stock—
Mikran PlantMetallurgy, machine building and electronics2 Thermax 5G 4L C absorption chillers, 2 cooling towers2 × 1,100 kW of cooling
Navoi Mining and Metallurgical CombineMetallurgy, machine building and electronicsNCT VR cooling tower, PU-330/50 pump skid, W2C—
Optikovolokonnye Sistemy PlantMetallurgy, machine building and electronics2 Thermax 2V 3K C gas-fired absorption chillers, 2 cooling towers—
SAS Industrial Radiator PlantMetallurgy, machine building and electronicsNCT SVA cooling tower, control panel—
Silica Metals LLPMetallurgy, machine building and electronicsNCT SVA-1 mini cooling tower, control panel—
Volzhsky Pipe PlantMetallurgy, machine building and electronics2 Thermax HS 50C-CU absorption chillers (replacing Trane)2 × 1,650 kW of cooling
Apsheronsk Woodworking ComplexWoodworking and building materialsThermax 2B 4L C steam-fired absorption chiller, 2 cooling towers1,500 kW of cooling
Lomo Woodworking ComplexWoodworking and building materialsThermax LT18 absorption chiller, cooling tower600 kW of cooling
Minsk Silicate Products PlantWoodworking and building materialsNCT SVA-1 mini cooling tower—
Tarkett-Sommer PlantWoodworking and building materialsThermax HS-40D-CU absorption chiller—
VMG Industri Woodworking FactoryWoodworking and building materialsNCT VR cooling tower, control panel, Thermax absorption chiller—
Arai City Mall Shopping CenterCommercial real estate2 Thermax absorption chillers, NCT VR cooling towers2 × 1,100 kW of cooling
Depo Shopping MallCommercial real estateThermax 5G-3L-C absorption chiller, cooling tower800 kW of cooling
Faiffs Property Holding Warehouse ComplexCommercial real estate2 Thermax gas-fired absorption chillers, NCT VR2S cooling towers2 × 1.2 MW of cooling
Maskarad Shopping MallCommercial real estate2 Thermax absorption chillers, NCT VR3 cooling tower, W2C water treatment850 + 1,350 kW of cooling
Mikhailovsky DelicatessenCommercial real estateThermax 5G 2B H absorption chiller, NCT SVA-4 mini cooling tower320 kW of cooling
Minvody Expo Multifunctional Exhibition CenterCommercial real estate2 Thermax 2V 4M C and 2V 5K C gas-fired absorption chillers2,001 + 1,702 kW of cooling
Nobel Park Business CenterCommercial real estateThermax hot-water-driven absorption chiller—
Omega Tower Business CenterCommercial real estateThermax LT 18C absorption chiller, NCT VR2 cooling tower—
Reef Residence HotelCommercial real estate2 Thermax 2V 2M C gas-fired absorption chillers, 2 cooling towers1,400 kW of cooling
Sultan-Palas HotelCommercial real estateThermax 2V 3K C gas-fired absorption chiller, 2 closed-circuit cooling towers1 MW of cooling
TAU Galereya Shopping MallCommercial real estate2 Thermax 5G 6L C absorption chillers2 × 2,200 kW of cooling
Triumf Plaza Shopping and Entertainment ComplexCommercial real estateThermax 5G 5K C absorption chiller, closed-circuit cooling towers—
Central Customs Directorate of the Russian FederationPublic buildings and sports2 Thermax LT-14 C absorption chillers2 × 500 kW of cooling
MOSGAZ OJSC Engineering CenterPublic buildings and sports2 Thermax GD 20C gas-fired absorption chillers, 4 cooling towers1,200 kW of cooling
Metrostroy Sports ComplexPublic buildings and sports2 Thermax 5G 3M C absorption chillers, cooling towers with sound attenuators2 × 925 kW of cooling
Moscow Region Government HousePublic buildings and sports3 Thermax LT42 T absorption chillers in a trigeneration system3,000 kW of cooling
Smolensk Academy of Physical Culture and SportsPublic buildings and sports2 Thermax 5G 4L C absorption chillers2 × 1,100 kW of cooling
International Tobacco Company, Leningrad RegionOther industries4 NCT VR cooling towers, control panels—
Moll-Elit Wallpaper PlantOther industriesNCT SVA cooling tower, W0C water treatment—

Detailed descriptions and photos are in the "Projects" section.

Why order a cooling system from one company rather than three contractors?

When the supplier, the designer and the installer are different companies, each one points at the others after a failed startup. We have manufacturing, design and installation in one company, so one contractor is responsible for the result.

  • No disputes at start-up. The final water temperature is the responsibility of the same team that calculated the scheme, made the equipment and installed it. We design for the real conditions of the site: if the site is in the Rostov Region, we size the chiller for +44 °C, not for the catalog +30 °C.
  • Our own plant. We have been making NCT equipment in Sertolovo since 2015, so delivery times and spare parts depend on us. NCT holds 40% of the market for modular fan-assisted cooling towers; since April 2024 NCT has been a member of the Cooling Technology Institute (CTI, USA), the first in Russia and the CIS. The production has passed audits by Gazprom and Rosatom.
  • Thermax from the official representative. Since 2011 we have installed more than 60 Thermax absorption chillers and hold 65% of the absorption chiller market in Russia: the machine is selected and started up by a team that knows how it is built.
  • Handover under load. We hand over the system after an integrated test run under process load, usually 72 hours, not after an idle start.

The equipment warranty is 12 months as standard, up to 5 years with our installation and a service contract, and 10 years against through-corrosion; the warranty on installation work is 24 months. The quality management system is certified to ISO 9001:2015, and our engineering center holds an SRO (self-regulatory organization) certificate.

Frequently asked questions

How is a cooling system different from air conditioning?

Air conditioning is one of the consumers of cooling. A cooling system prepares chilled water or glycol and distributes it to all consumers at once: air handling units and fan coils, machine tools, reactors, server rooms. That is why it is sized for the total load of the plant or building, with redundancy and a winter mode, rather than for a single room.

How much electricity does free cooling save?

It depends on the water temperature and the climate. In Moscow, the wet-bulb temperature stays below 5 °C for 4,696 hours a year, more than half the year. For 1 MW of year-round load, that is up to 1.78 million kWh a year that the compressors do not consume. Thresholds and schemes are in the article "Free cooling in industry" (in Russian).

The design is good, but there is no money for the whole system this year. Can we do it in phases?

Yes, if you split it into phases from the start. First the design and whatever is expensive to redo later: space for the next machines, headers with capped branches, spare room in the control panel. We start up the first phase for the current load and connect the following ones without major rework. Ordering the design, equipment and installation piecemeal from different contractors, on the other hand, ends up more expensive: the corrections fall on you. A pre-design study with options also helps defend the budget for the next cycle.

Which outdoor air temperature should be used in the calculation? Determine it yourselves from your climate data.

We will, but you confirm the figure in the specification, because it determines what happens in hot weather. We start with SP 131.13330 (Russian building code), then look at long-term hourly data and the site itself: a calculation based only on the code's design points can leave the system 20–30% short of capacity in summer. For critical processes we take a higher temperature. Do not understate the humidity either: selection for dry air comes out cheaper but may not cope in summer. What happens above the design point we record separately.

Operating points may change after the design. How will this affect the price?

It will, if the condition was not agreed in advance. A changed pump operating point may require a different pump, and a changed operating point of the whole system may affect other equipment too. So we agree in advance which parameters are the baseline, what tolerance is included in the price and how we recalculate. Changes are easier to make before manufacturing starts; after that it means reworking finished assemblies.

The price went up while we were getting the lease approved. Can you keep the price from the first proposal?

Not always. Some components are tied to exchange rates, and the price may change during the approval period. To avoid this, check the validity period of the proposal and allow time for the leasing company and the lawyers: a long approval process is what eats up the first price. If the proposal is about to expire, write to us in advance: we will check the price before the leasing company issues its documents.

We will survey the site and select and calculate the system free of charge: send a request or call +7 (800) 333-49-96.

Let us size a cooling system for your site

An engineer will select the equipment and send you a calculation. Free of charge, no obligation.

Contact us